The concession

What was promised at Marsa, with the published documents and clauses.

The grass project our members had already started

2010. We obtained permits to convert Marsa into an international-standard grass field. Members paid for the permits and initial works in full, without outside funding.

2011. We lifted the original soil, backfilled the ground, raised the surface slightly and formed a camber to help rainwater drain away. We then relaid the soil. On advice, we gave the field time to settle so we could identify and correct any ponding before planting turf.

By 2014 we were satisfied with how the ground performed and ready to complete the project. As the final phase began, the Ministry instructed us to stop because the field was to form part of the wider Marsa redevelopment.

How the concession changed the plan

The Government issued the formal request for proposals on 19 June 2015. The MRTL consortium was the sole bidder. An €18 million investment was announced in 2017. A €28 million investment in the wider project was announced when Parliament approved it in July 2019. Marsa Race Track Limited dates the signing of the concession to 18 February 2022. The development included commercial premises and facilities for the care and rehabilitation of horses. Read MRTL’s project chronology.

While our own project remained on hold, we met MRTL repeatedly. We needed to know whether the Club could commit to lessons, fixtures and visiting teams if the field was also wanted for commercial events. Those discussions never produced a final operating agreement between MRTL and the Club. Years later, when we handed over the ground, being able to plan the next season still depended on knowing exactly when our field would be available.

Read the Marsa field timeline

The parliamentary record

What MRTL undertook.

The 2019 parliamentary approval and the 2022 signing were separate steps. These provisions appear in the text laid before Parliament with Motion 572. Each link below opens the relevant document page.

Who pays for the remaining works?

Clauses 6.4 and 6.5 put design, construction and infrastructure financing on the grantee, with the grantor providing services to the site boundary. Clause 20.1 commits at least €24 million to sports facilities across the whole project. The €24 million figure is the minimum for sports facilities in this clause. The €28 million announced in 2019 covered the wider redevelopment. The text gives no separate investment figure for polo.

Construction costs · PDF p. 119 · Investment · p. 135

What kind of pitch?

Clause 6.8(b) calls for FIP-compliant dimensions and boards, and floodlighting. Clause 12.1(ii–iii) requires MRTL to establish grass and maintain and irrigate the surface. A return to the former surface is conditional on grass proving unsuitable, discussion with the club and government approval.

Grass and irrigation · PDF p. 125

How long without polo or a clubhouse?

Clause 12.1(vii) anticipates about nine months of suspended play while the surface is laid and calls for efforts to identify a practice area. Clause 12.2 provides for a clubhouse of about 190 m² in basic finished condition. Members recall being told to expect one year without it. That period is the club’s account of the promise.

Playing arrangements and clubhouse · PDF p. 126