17 months without polo at Marsa.
The timeline, the impact on our club and what we are asking for now.
Our club · Our home
We handed over our home.
We are still waiting for its return.
In 2024, MRTL told us permits were progressing and works would start in 2025. After the Cawnpore Cup on 21 June 2025 we handed over the main field and cleared our clubhouse. Our understanding was that a playable interim field would allow the season to resume that September.

Our club and its members are under enormous pressure. This is Malta’s only polo pitch: there is no other home ground on the island to which we can move our matches or academy. Members continue to care for their horses and meet the costs while the future of the sport remains uncertain.
The concession brings obligations to invest in equestrian sport alongside rights to commercial development at the site. The sporting facilities must be delivered. Our members need a funded programme, firm completion dates and a return to polo—not further explanations for delay.
The concession anticipated about nine months of suspended play while the surface was laid. Our handover discussions covered two phases, with an interim surface so that we could play between them. The dates below record what the Club understood would happen. Read the written concession provisions.
The field at Marsa
The Marsa field timeline
- 2010–2014 · The Club’s project
In 2010, members paid for permits to convert the pitch to grass. In 2011, we lifted the soil, raised and shaped the ground to reduce flooding, and relaid the soil. We let the ground settle so we could correct any low spots before planting. By 2014 we were satisfied with the drainage and ready to finish. The Ministry then asked us to stop. Read the history of the works.
- June 2025 · The handover timetable
We understood that MRTL would return a playable interim field in September 2025, take it back in May 2026 to correct the surface and lay the turf, and deliver the completed grass field with its maintenance equipment in October 2026. The September return never happened.
- Committee oversight and Battro’s inspections
Our committee followed progress with Battro, the Club’s specialist polo-field advisers. Battro visited Marsa several times to inspect the work and sent written reports identifying corrections. As a committee, we used those reports to follow up with MRTL. Read about Battro’s field design.
- February 2026 · The revised programme
MRTL, Government officials and the Club met to revise the timetable. A programme headed Polo Pitch POW v1 was circulated. Members saw some activity resume. The Club also filed a judicial protest that February.
For the pitch, the programme scheduled sample approval by 16 March 2026, the silica-sand topping by 30 April 2026, a test patch by 11 May 2026 and seeding by 18 May 2026. Turf testing and approval were scheduled for 21 September to 30 October 2026. The original handover timetable had envisaged a completed field that October.
Clubhouse drawings were scheduled for completion by 21 May 2026, with construction from 22 May to 26 November 2026. Permits and approvals for reverse osmosis ran into March 2027, with installation scheduled to finish on 30 April 2027.

Enlarge the February 2026 works programme - May 2026 · Battro’s fourth report
The report set out the proposed construction layers, including the sand and soil in which the grass would take root.
- 24 November 2026 · The field has never been handed back
The scheduled sand topping is still missing. The main field remains unusable, and our clubhouse has yet to be replaced. MRTL points to the underground works it has carried out and identifies water supply as its main concern. The Club has secured boreholes and identified a reverse-osmosis option.
The main field has never been handed back

Our members saw coarse material deposited and compacted on the field. Grass grew over holes and humps. We were concerned about a loose horse straying onto the uneven ground from the racetrack. The Club asked Animal Welfare to visit. We saw no substantive intervention and received no report.
Exposed stones pose a danger to our ponies’ hooves. We cannot use the field in this condition. Two reservoirs have been built, but the main pitch still has no installed irrigation system or floodlights. We are concerned that installing them will mean opening trenches again.
What happened to our clubhouseThe answer our members need now.
The club says the main pitch remains unfinished. MRTL says it has carried out extensive works, including underground reservoirs, and identifies water supply as its main obstacle. MRTL must give the club a clear delivery programme for both the pitch and the replacement clubhouse: committed funding, construction milestones and handover dates. The loss of our meeting place cannot remain an afterthought to discussions about turf.
For our friends in polo.
To fellow clubs, players and supporters abroad, thank you for taking an interest in Malta Polo Club. Sharing our story and bringing experience in grounds, club development or fundraising can help us work towards a return to polo at Marsa.